© 2018 by STAMGAZSTROY - All rights reserved

  • LinkedIn - White Circle

Contract for the Procurement, Fabrication, Load-Out and Transportation of Topside for EPC Cluster 4 within the Kashagan Experimental Project, with execution of works in "Temir At" yard.
 
Briefly the Scope of Work consists of: Endorsement of Detail Engineering Package;
 
• Procurement of project materials, Shop Drawings, Method Statements;
 
• Fabrication/Construction works by KCOI;
 
• Electrical/Instrumentation/Telecom Installation works by consortium partner
 
• Load – Out Procedures and Load – Out Operation by skidding a 1500 tons module on barge to be transported offshore.

CONTRACTORS AND FINAL CLIENTS

EPC CLUSTER 4

TOPSIDE

PROJECT DETAILS

For the project we mobilised the following personnel: Welders, Steel Fitters, Pipe Fitters, Riggers, Foremen, Welding Supervisors, Welding Inspectors, HSE Inspectors, QC Inspectors and Coordinators.

188

2017

5

Personnel of the following nationalities: Kazakhs, Italians, Indians, Filipinos and Thais.

The project has an estimated duration of 3 years, with a delivery date for 2019.

MOBILISED

PERSONNEL

DIFFERENT

NATIONALITIES

THE STARTING DATE

OF THE PROJECT