FLOATING UNITS

KASHAGAN PROJECT

In the year 2015, we built and assembled all the floating units required for laying  the offshore pipeline of the Kashagan project. All activities were done by our technicians under supervision and coordination of our site manager.

PROJECT DETAILS

1.533

PRODUCED

UNITS

We built and delivered a total of 1533 floating units  which were then transported offshore to the Kashagan field.

4

DIFFERENT

NATIONALITIES

We mobilised a total of 133 personnel from the following nationalities: Kazakh, Italians, Thais and Romanians.

2015

THE STARTING DATE

OF THE PROJECT

Project started in 2015 and was completed in just 4 months, totally in line with client’s expectations.