The project was executed in the northern territories of the Caspian Sea in the Republic of Kazakhstan
The scope of work includes the replacement of onshore oil and gas trunk lines, the swamp section and shallow water sections. 


It also includes upgrading of the 5 onshore valve stations, with valve replacement.

CONTRACTORS AND FINAL CLIENTS

KASHAGAN

PIPELINE REPLACEMENT

PROJECT DETAILS

We mobilised mostly direct personnel as: welders, grinders, riggers, and pipe fitters. And indirect as: welding inspectors, welding supervisors, piping supervisors, HSE inspectors, and QA/QC inspectors.

815

2015

6

The following nationalities was mobilized on the project: Kazakhs, Italians, Thais, Romanians, Indians, and Turkish.

The project started in March 2015 and was completed according the forecast at the end of June 2016.

MOBILISED

PERSONNEL

DIFFERENT

NATIONALITIES

THE STARTING DATE

OF THE PROJECT